← PortfolioCooper's HawkMid-Year Review · FY26
Operations

In Restaurant Conversion Project: Phase 3 (ENTERPRISE)

CH Master Project TrackerEnterpriseTraffic/Marketing System: Performance Driving Strategy (ENTERPRISE)In Restaurant Conversion Project: Phase 3 (ENTERPRISE)4 sub-projects

Goals: 1. Create a WC Culture that is supportive, simple to understand and accountable 2. Revised thoughtful inventive program 3. Create training on WC Coaching

Stage
In Flight
Sub-projects
4
Health
In Progress/On Track
Latest Update · Feb 2, 2026

9.9.25: Pilot system in FY25 Q4 with launch in FY26 Q12.2.26 (Bryan): Pilot documentation underway. Shooting for a mid march pilot and a June rollout brand wide.

Department
Operations
Strategic Pillar
1 ACQUIRE NEW MEMBERS
Executive Sponsor
Jason P
Owner
Bryan W
IT Dependency
IT Roadmap
Fiscal Year / Quarter
FY26
Timing
Start Date
Target End
Budget
Status
In Progress/On Track
Status Updates · 7
2y 10m running
In Progress/On TrackFeb 2, 2026

9.9.25: Pilot system in FY25 Q4 with launch in FY26 Q12.2.26 (Bryan): Pilot documentation underway. Shooting for a mid march pilot and a June rollout brand wide.

In Progress/On TrackSep 9, 2025

9.9.25: Pilot system in FY25 Q4 with launch in FY26 Q1

Not StartedMay 21, 2024

5.21.2024: working phase 2 in progress with focus on upgrades and cancels.

Not StartedMar 21, 2024

3.21.24: holding for resource

Not StartedDec 24, 2023

12.24.23: Moving to Ops 2024

DeferredDec 6, 2023

11.28.23: Deferred to 2025 (pending completion of Phase 2 and further assessment)

PendingAug 31, 2023

Pending completion of Phase 2 and further assessment