Facilities

Fire Suppression: New/System Test

Facilities ProjectsFire Suppression: New/System Test
Stage
In Flight
Level
Level 3: Dept Project
Health
Pending
Latest Update · Jun 29, 2026

6.29.26 [Jeremy]: Lauren and Bob are working to implement into future designs where possible

Department
Facilities
Strategic Pillar
Not Applicable
Executive Sponsor
Dawn P
Owner
IT Dependency
No
IT Roadmap
Fiscal Year / Quarter
FY26
Timing
Start Date
Target End
Budget
Status
Pending
Status Updates · 7
10 months running
In Progress/On TrackJun 29, 2026

6.29.26 [Jeremy]: Lauren and Bob are working to implement into future designs where possible

PendingJun 29, 2026

6.29.26 [Jeremy]: Continues to be pending input from Development (Lisa); believe there are potential savings and reduced downtime (limited investment w/potential upside); no retro - if aligned, would ultimately move to Construction as the owner

PendingMar 14, 2026

3.13.26 [Jeremy]: Pending input from Development (Lisa); believe there are potential savings and reduced downtime; if aligned, would ultimately move to Construction as the owner

ApprovedFeb 9, 2026

10.21.25 (Jeremy):Researching for new restaurants only, can't be retrofittedWorking with construction on incorporating in design No cost to this - will just be a different ansul installed in the new NRO's but we will not be retrofitting 2.6.26 (Jeremy): MEP needs to vet spec, This would be research in 2026 as it would have to be built into the building design, No retros

ProposedFeb 9, 2026

10.21.25 (Jeremy):Researching for new restaurants only, can't be retrofittedWorking with construction on incorporating in design No cost to this - will just be a different ansul installed in the new NRO's but we will not be retrofitting 2.6.26 (Jeremy): MEP needs to vet spec, This would be research in 2026 as it would have to be built into the building design, No retros

ProposedOct 21, 2025

Researching for new restaurants only, can't be retrofittedWorking with construction on incorporating in design No cost to this - will just be a different ansul installed in the new NRO's but we will not be retrofitting

ProposedSep 1, 2025
Admin Note

Needs cross-functional support/input from Development (Lisa)