← PortfolioCooper's HawkMid-Year Review · FY26
Facilities

Utilities: Optimization

Facilities ProjectsUtilities: Optimization

Company under evaluation; considerable savings - exploring

Stage
Discover (Blue Sky)
Level
Level 3: Dept Project
Health
Pending
Latest Update · Apr 14, 2026

4.13.26 DF: Proceed with validation and execution in regulated states. Expand analysis to deregulated states and compare performance against the current energy partner.

Department
Facilities
Strategic Pillar
Executive Sponsor
Jason P
Owner
IT Dependency
IT Roadmap
Fiscal Year / Quarter
FY26
Timing
Start Date
Target End
Budget
Status
Pending
Status Updates · 5
6 months running
In Progress/On TrackApr 14, 2026

4.13.26 DF: Proceed with validation and execution in regulated states. Expand analysis to deregulated states and compare performance against the current energy partner.

PendingMar 22, 2026

3.18.26 [Strat Mtg]: team requested to see potential output to better understand the potential opportunity if Jeremy's early discovery yields positive results

PendingMar 15, 2026

3.13.26: project had been cancelled however a new vendor has been identified; potential for significant savings; current discovery

CancelledFeb 4, 2026

2.4.26 per Jeremy: Remove, this is energy savings related to the smart restaurant project. We're already monitoring usage + rates.

Not StartedDec 28, 2025

Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26