Asset Tagging
3.13.26 [Jeremy]: Test in Livonia next week; then roll in 2 NROs
3.13.26 [Jeremy]: Test in Livonia next week; then roll in 2 NROs
1.13.26 [Jeremy Lyle] Selected provider did not work out. We have selected a new provider and moving forward with them to have rolled out in Q1 or Q2 2026. All restaurants are tagged.
1.13.26 [Jeremy Lyle] Selected provider did not work out. We have selected a new provider and moving forward with them to have rolled out in Q1 or Q2 2026.
10.15.24 [YE}: All restaurants tagged; cleaning data and introducing to the system; on track for Q4 completion
6.11.24 (LT): in progress; targeting completion in ~2 months (mid-Aug)
4.17.24: Tagging began 4.15.24; estimated to be complete in ~3 months
12.22.23: By tomorrow we should receive the final proposal and timeline. If we agree to this we would like to perform tagging at one restaurant by the 2nd week of Jan to determine scope to help finalize timeline. Pending the approval of the proposal and that the scope work at the test location doesn't change anything we feel we should be able to have the project done by the end of Q1. 11.28.23: moved to 2024 (deferred from 23)
11.28.23: moved to 2024 (deferred from 23)
7.18.23 (mid year): Deferred to 2024