← PortfolioCooper's HawkMid-Year Review · FY26
IT

Apple Pay (TR, DR, Bar)

IT (Technology) ProjectsRestaurant Ops [PARENT]Apple Pay (TR, DR, Bar)

Enable EMV device to process Apple Pay in TR; How does this work with our current system of tethering the EMV?

Stage
Launch (Activate)
Level
Level 0: Inactive
Health
In Progress/On Track
Latest Update · May 20, 2026

5.20.26 (IT Prioritization outcomes): business case needed.

Department
IT
Strategic Pillar
3 OPTIMIZE PERFORMANCE
Executive Sponsor
Dave H
Owner
James N
IT Dependency
Yes
IT Roadmap
Biz Case Needed
Fiscal Year / Quarter
FY25 · Q4
Timing
P12
Start Date
Target End
Budget
Status
In Progress/On Track
Status Updates · 9
2y 3m running
On-holdMay 20, 2026

5.20.26 (IT Prioritization outcomes): business case needed.

In Progress/On TrackNov 24, 2025
CompleteNov 24, 2025
On-holdNov 13, 2024
BehindOct 9, 2024

10.4.24: Shift timing with Simphony (moving to 2025)

In Progress/On TrackApr 29, 2024

4.10.24: Prepping for test in the RSC Lab

In Progress/On TrackApr 29, 2024

4.10.24: Prepping for test

Not StartedApr 10, 2024

4.10.24: Added to project list. IT Intake Form submitted.

Not StartedApr 10, 2024

4.10.24: Added to project list per Tom R from Tim