← PortfolioCooper's HawkMid-Year Review · FY26
IT

Data Privacy

IT (Technology) ProjectsCyber & Compliance [PARENT]Data Privacy
Stage
Not Started
Level
Level 3: Dept Project
Health
Behind (delayed)
Latest Update · Jun 29, 2026

4.6.26 James: Needs definition. Deferred to 2027+.

Department
IT
Strategic Pillar
3 OPTIMIZE PERFORMANCE
Executive Sponsor
Dave H
Owner
Shay R
IT Dependency
Yes
IT Roadmap
Yes
Fiscal Year / Quarter
FY26 · Q1
Timing
Start Date
Target End
Budget
Status
Behind (delayed)
Status Updates · 3
2y 3m running
DeferredJun 29, 2026

4.6.26 James: Needs definition. Deferred to 2027+.

BehindJun 17, 2024

6.12.24: Not started/behind (per Susan)

In Progress/On TrackApr 3, 2024

3.19.24: In Progress (IT SC)

Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26