← PortfolioCooper's HawkMid-Year Review · FY26
Retail

Decanter Next Generation Designs

Retail ProjectsDecanter Next Generation Designs

Decanter concept and prototype development with designer (Carter McGuyer); present to leadership and user focus group 8.2.23 for review and feedback; if approved will work toward earliest launch date possible

Stage
In Flight
Level
Level 3: Dept Project
Health
In Progress/On Track
Latest Update · Apr 10, 2026

4.6.26 (DF): We will not pursue a holiday test based on the presented designs. Continue pursuing a premium, fully reimagined design rather than a stop‑gap solution.

Department
Retail
Strategic Pillar
5 INNOVATE & EXPLORE
Executive Sponsor
Tom K
Owner
Sarah B
IT Dependency
No
IT Roadmap
Fiscal Year / Quarter
FY26 · Q4
Timing
in market by Oct, 2026
Start Date
Target End
Budget
Status
In Progress/On Track
Status Updates · 9
2y 11m running
In Progress/On TrackApr 10, 2026

4.6.26 (DF): We will not pursue a holiday test based on the presented designs. Continue pursuing a premium, fully reimagined design rather than a stop‑gap solution.

In Progress/On TrackFeb 11, 2026

2.11.26: Targeting DF mid/end March; if sign off, rollout potentially Q4 2026 or Q1 2027

In Progress/On TrackJan 7, 2026

9.17.25: restart design with brainstorming exercise (see notes); goal: in market by Oct, 2026 10.28.25: $20K in 2026 budget for Decanter redesign/Prototypes 1.5.26 Tim notes: 3D printing / Engraved / temp / electric cooling (batteries) / simply modernize Grapevine (take curves out)

In Progress/On TrackOct 28, 2025

9.17.25: restart design with brainstorming exercise (see notes); goal: in market by Oct, 2026 10.28.25: $20K in 2026 budget for Decanter redesign/Prototypes

In Progress/On TrackSep 17, 2025

9.17.25: restart design with brainstorming exercise (see notes); goal: in market by Oct, 2026

BehindMay 22, 2024

5.22.2024: Frame is signed off on. New Funnel & Aerator Designs are being 3-D printed and due to arrive the week of 5/13/24.

BehindJan 5, 2024

12.20.23 year-end: Date of New Samples. Arrival Jan Week 1. Review at earliest Decision Forum. 8.1.24 Target In-Restaurant Date 9.13.23: Design update in progress; launch expected Spring/Summer 24

In Progress/On TrackOct 3, 2023

9.13.23: Design update in progress; launch expected Spring/Summer 24

In Progress/On TrackAug 2, 2023

7.20.23 (mid year): designer prototype review and user focus group on 8.2; launch/timeline pending outcome of leadership reviews