Ops Development
MTMX Expansion Plan
MTMX Expansion Plan
Expanding the MTMX to Wheeling, Ashburn, St. Peters, Reston, Morton Grove, Town & Country, & Gilbert.
Health
Complete
Latest Update · Mar 26, 2024
12.8.23 YE: projecting 32-35 at YE; complete by FY24 Q2
Department
Ops Development
Strategic Pillar
1 ENHANCE THE CORE BUSINESS
Executive Sponsor
Jason P
Owner
Tom R
IT Dependency
—
IT Roadmap
—
Fiscal Year / Quarter
FY24 · Q2
Timing
Full rollout by FY24 Q2
Start Date
Nov 1, 2022
Target End
—
Budget
—
Status
Complete
Status Updates · 5
3y 8m running
CompleteMar 26, 2024
12.8.23 YE: projecting 32-35 at YE; complete by FY24 Q2
In Progress/On TrackDec 25, 2023
12.8.23 YE: projecting 32-35 at YE; complete by FY24 Q2
In Progress/On TrackAug 2, 2023
7.23: targeting full rollout/completion by FY24 Q2
In Progress/On TrackJan 10, 2023
At riskDec 28, 2022
Not much traction on the job posting. Only 9 applicants and only 2 of those made it through the initial screening.