← PortfolioCooper's HawkMid-Year Review · FY26
Supply Chain

Smallware RFP

Smallware RFP
Stage
In Flight
Level
Health
In Progress/On Track
Latest Update · Jan 8, 2026

1.8.26: Complete & can be closed out, per Jeremy L.

Department
Supply Chain
Strategic Pillar
3 OPTIMIZE PERFORMANCE
Executive Sponsor
CFO
Owner
IT Dependency
IT Roadmap
Fiscal Year / Quarter
FY25 · Q3
Timing
Q3 25
Start Date
Target End
Budget
Status
In Progress/On Track
Status Updates · 3
2y 2m running
CompleteJan 8, 2026

1.8.26: Complete & can be closed out, per Jeremy L.

In Progress/On TrackOct 15, 2024

10.15.24 [YE]: extended current agreement through June 25; push out until then

In Progress/On TrackMay 9, 2024

5.9.2024: Bid out Smallware provider

Project Action

Status Needed

Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26